What is client-server and web based testing and how to test these applications

Question:

What is the difference between client-server testing and web based testing and what are things that we need to test in such applications?

Ans:
Projects are broadly divided into two types of:

  • 2 tier applications
  • 3 tier applications

CLIENT / SERVER TESTING
This type of testing usually done for 2 tier applications (usually developed for LAN)
Here we will be having front-end and backend.

The application launched on front-end will be having forms and reports which will be monitoring and manipulating data

E.g: applications developed in VB, VC++, Core Java, C, C++, D2K, PowerBuilder etc.,
The backend for these applications would be MS Access, SQL Server, Oracle, Sybase, Mysql, Quadbase

The tests performed on these types of applications would be
- User interface testing
- Manual support testing
- Functionality testing
- Compatibility testing & configuration testing
- Intersystem testing

WEB TESTING
This is done for 3 tier applications (developed for Internet / intranet / xtranet)
Here we will be having Browser, web server and DB server.

The applications accessible in browser would be developed in HTML, DHTML, XML, JavaScript etc. (We can monitor through these applications)

Applications for the web server would be developed in Java, ASP, JSP, VBScript, JavaScript, Perl, Cold Fusion, PHP etc. (All the manipulations are done on the web server with the help of these programs developed)

The DBserver would be having oracle, sql server, sybase, mysql etc. (All data is stored in the database available on the DB server)

The tests performed on these types of applications would be
- User interface testing
- Functionality testing
- Security testing
- Browser compatibility testing
- Load / stress testing
- Interoperability testing/intersystem testing
- Storage and data volume testing

A web-application is a three-tier application.
This has a browser (monitors data) [monitoring is done using html, dhtml, xml, javascript]-> webserver (manipulates data) [manipulations are done using programming languages or scripts like adv java, asp, jsp, vbscript, javascript, perl, coldfusion, php] -> database server (stores data) [data storage and retrieval is done using databases like oracle, sql server, sybase, mysql].

The types of tests, which can be applied on this type of applications, are:
1. User interface testing for validation & user friendliness
2. Functionality testing to validate behaviors, i/p, error handling, o/p, manipulations, services levels, order of functionality, links, content of web page & backend coverage's
3. Security testing
4. Browser compatibility
5. Load / stress testing
6. Interoperability testing
7. Storage & data volume testing

A client-server application is a two tier application.
This has forms & reporting at front-end (monitoring & manipulations are done) [using vb, vc++, core java, c, c++, d2k, power builder etc.,] -> database server at the backend [data storage & retrieval) [using ms access, sql server, oracle, sybase, mysql, quadbase etc.,]

The tests performed on these applications would be
1. User interface testing
2. Manual support testing
3. Functionality testing
4. Compatibility testing
5. Intersystem testing
Some more points to clear the difference between client server, web and desktop applications:

Desktop application:
1. Application runs in single memory (Front end and Back end in one place)
2. Single user only

Client/Server application:
1. Application runs in two or more machines
2. Application is a menu-driven
3. Connected mode (connection exists always until logout)
4. Limited number of users
5. Less number of network issues when compared to web app.

Web application:
1. Application runs in two or more machines
2. URL-driven
3. Disconnected mode (state less)
4. Unlimited number of users
5. Many issues like hardware compatibility, browser compatibility, version compatibility, security issues, performance issues etc.

As per difference in both the applications come where, how to access the resources. In client server once connection is made it will be in state on connected, whereas in case of web testing http protocol is stateless, then there comes logic of cookies, which is not in client server.

For client server application users are well known, whereas for web application any user can login and access the content, he/she will use it as per his intentions.

So, there are always issues of security and compatibility for web application.

Software Testing Certifications

International Certifications:

1) Foundation Level :
Know more at : http://www.istqb.org/fileadmin/media/SyllabusFoundation.pdf
2) Advanced Level :
Know more at : http://www.istqb.org/fileadmin/media/SyllabusAdvanced.pdf

QA institute certifications :

1) Certified Software Tester (CSTE) :
know more at : http://www.softwarecertifications.org/qai_cste.htm
2) Certified Software Quality Analyst (CSQA) :
know more at : http://www.softwarecertifications.org/qai_cqa.htm
3) Certified Software Project Manager (CSPM) :
know more at : http://www.softwarecertifications.org/qai_cspm.htm

International institute of software testing:

1) Certified Software Test Professional (CSTP) :
know more at : http://www.testinginstitute.com/cstp.php
2) Certified Test Manager (CTM) :
know more at : http://www.testinginstitute.com/ctm.php

Test plan sample: SoftwareTesting and Quality assurance Templates

Test plan is in high demand. Ya it should be! Test plan reflects your entire project testing schedule and approach. This article is in response to those who have demanded sample test plan.
 
Test plan will include the purpose of test plan i. e to prescribe the scope, approach, resources, and schedule of the testing activities. To identify the items being tested, the features to be tested, the testing tasks to be performed, the personnel responsible for each task, and the risks associated with this plan.
 

Test Plan Template:

(Name of the Product)

Prepared by:

(Names of Preparers)

(Date)

TABLE OF CONTENTS

1.0 INTRODUCTION

2.0 OBJECTIVES AND TASKS
2.1 Objectives
2.2 Tasks

3.0 SCOPE

4.0 Testing Strategy
4.1 Alpha Testing (Unit Testing)
4.2 System and Integration Testing
4.3 Performance and Stress Testing
4.4 User Acceptance Testing
4.5 Batch Testing
4.6 Automated Regression Testing
4.7 Beta Testing

5.0 Hardware Requirements

6.0 Environment Requirements
6.1 Main Frame
6.2 Workstation

7.0 Test Schedule

8.0 Control Procedures

9.0 Features to Be Tested

10.0 Features Not to Be Tested

11.0 Resources/Roles & Responsibilities

12.0 Schedules

13.0 Significantly Impacted Departments (SIDs)

14.0 Dependencies

15.0 Risks/Assumptions

16.0 Tools

17.0 Approvals

1.0 INTRODUCTION

A brief summary of the product being tested. Outline all the functions at a high level.

2.0 OBJECTIVES AND TASKS

2.1 Objectives
Describe the objectives supported by the Master Test Plan, eg., defining tasks and responsibilities, vehicle for communication, document to be used as a service level agreement, etc.

2.2 Tasks
List all tasks identified by this Test Plan, i.e., testing, post-testing, problem reporting, etc.
3.0 SCOPE

General
This section describes what is being tested, such as all the functions of a specific product, its existing interfaces, integration of all functions.

Tactics
List here how you will accomplish the items that you have listed in the "Scope" section. For example, if you have mentioned that you will be testing the existing interfaces, what would be the procedures you would follow to notify the key people to represent their respective areas, as well as allotting time in their schedule for assisting you in accomplishing your activity?

4.0 TESTING STRATEGY

Describe the overall approach to testing. For each major group of features or feature combinations, specify the approach which will ensure that these feature groups are adequately tested. Specify the major activities, techniques, and tools which are used to test the designated groups of features.

The approach should be described in sufficient detail to permit identification of the major testing tasks and estimation of the time required to do each one.

4.1 Unit Testing

Definition:
Specify the minimum degree of comprehensiveness desired. Identify the techniques which will be used to judge the comprehensiveness of the testing effort (for example, determining which statements have been executed at least once). Specify any additional completion criteria (for example, error frequency). The techniques to be used to trace requirements should be specified.

Participants:
List the names of individuals/departments who would be responsible for Unit Testing.

Methodology:
Describe how unit testing will be conducted. Who will write the test scripts for the unit testing, what would be the sequence of events of Unit Testing and how will the testing activity take place?

4.2 System and Integration Testing

Definition:
List what is your understanding of System and Integration Testing for your project.

Participants:
Who will be conducting System and Integration Testing on your project? List the individuals that will be responsible for this activity.

Methodology:
Describe how System & Integration testing will be conducted. Who will write the test scripts for the unit testing, what would be sequence of events of System & Integration Testing, and how will the testing activity take place?

4.3 Performance and Stress Testing

Definition:
List what is your understanding of Stress Testing for your project.

Participants:
Who will be conducting Stress Testing on your project? List the individuals that will be responsible for this activity.

Methodology:
Describe how Performance & Stress testing will be conducted. Who will write the test scripts for the testing, what would be sequence of events of Performance & Stress Testing, and how will the testing activity take place?

4.4 User Acceptance Testing

Definition:
The purpose of acceptance test is to confirm that the system is ready for operational use. During acceptance test, end-users (customers) of the system compare the system to its initial requirements.

Participants:
Who will be responsible for User Acceptance Testing? List the individuals' names and responsibility.

Methodology:
Describe how the User Acceptance testing will be conducted. Who will write the test scripts for the testing, what would be sequence of events of User Acceptance Testing, and how will the testing activity take place?

4.5 Batch Testing

4.6 Automated Regression Testing

Definition:
Regression testing is the selective retesting of a system or component to verify that modifications have not caused unintended effects and that the system or component still works as specified in the requirements.

Participants:
Methodology:

4.7 Beta Testing
Participants:

Methodology:
5.0 HARDWARE REQUIREMENTS
Computers
Modems

6.0 ENVIRONMENT REQUIREMENTS

6.1 Main Frame
Specify both the necessary and desired properties of the test environment. The specification should contain the physical characteristics of the facilities, including the hardware, the communications and system software, the mode of usage (for example, stand-alone), and any other software or supplies needed to support the test. Also specify the level of security which must be provided for the test facility, system software, and proprietary components such as software, data, and hardware.

Identify special test tools needed. Identify any other testing needs (for example, publications or office space). Identify the source of all needs which are not currently available to your group.

6.2 Workstation
7.0 TEST SCHEDULE

Include test milestones identified in the Software Project Schedule as well as all item transmittal events.

Define any additional test milestones needed. Estimate the time required to do each testing task. Specify the schedule for each testing task and test milestone. For each testing resource (that is, facilities, tools, and staff), specify its periods of use.

8.0 CONTROL PROCEDURES

Problem Reporting
Document the procedures to follow when an incident is encountered during the testing process. If a standard form is going to be used, attach a blank copy as an "Appendix" to the Test Plan. In the event you are using an automated incident logging system, write those procedures in this section.

Change Requests
Document the process of modifications to the software. Identify who will sign off on the changes and what would be the criteria for including the changes to the current product. If the changes will affect existing programs, these modules need to be identified.

9.0 FEATURES TO BE TESTED

Identify all software features and combinations of software features that will be tested.

10.0 FEATURES NOT TO BE TESTED

Identify all features and significant combinations of features which will not be tested and the reasons.

11.0 RESOURCES/ROLES & RESPONSIBILITIES

Specify the staff members who are involved in the test project and what their roles are going to be (for example, Mary Brown (User) compile Test Cases for Acceptance Testing). Identify groups responsible for managing, designing, preparing, executing, and resolving the test activities as well as related issues. Also identify groups responsible for providing the test environment. These groups may include developers, testers, operations staff, testing services, etc.

12.0 SCHEDULES

Major Deliverables
Identify the deliverable documents. You can list the following documents:
- Test Plan
- Test Cases
- Test Incident Reports
- Test Summary Reports

13.0 SIGNIFICANTLY IMPACTED DEPARTMENTS (SIDs)

Department/Business Area Bus. Manager Tester(s)

14.0 DEPENDENCIES

Identify significant constraints on testing, such as test-item availability, testing-resource availability, and deadlines.

15.0 RISKS/ASSUMPTIONS

Identify the high-risk assumptions of the test plan. Specify contingency plans for each (for example, delay in delivery of test items might require increased night shift scheduling to meet the delivery date).
16.0 TOOLS
List the Automation tools you are going to use. List also the Bug tracking tool here.

17.0 APPROVALS

Specify the names and titles of all persons who must approve this plan. Provide space for the signatures and dates.

Name (In Capital Letters) Signature Date

1.

2.

3.

4.

What is actual testing process in practical or company environment?

Here I focus on software Testing actual working process in the companies. As of now I got good experience of software testing career and day to day testing activities.  So I will try to share more practically rather than theoretically.

Whenever we get any new project there is initial project familiarity meeting. In this meeting we basically discuss on who is client? what is project duration and when is delivery? Who is involved in project i.e manager, Tech leads, QA leads, developers, testers etc etc..?

From the SRS (software requirement specification) project plan is developed. The responsibility of testers is to create software test plan from this SRS and project plan. Developers start coding from the design. The project work is devided into different modules and these project modules are distributed among the developers. In meantime testers responsibility is to create test scenario and write test cases according to assigned modules. We try to cover almost all the functional test cases from SRS.  The data can be maintained manually in some excel test case templates or bug tracking tools.

When developers finish individual modules, those modules are assigned to testers.  Smoke testing is performed on these modules and if they fail this test, modules are reassigned to respective developers for fix. For passed modules manual testing is carried out from the written test cases. If any bug is found that get assigned to module developer and  get logged in bug tracking tool. On bug fix tester do bug verification and regression testing of all related modules. If bug passes the verification it is marked as verified and marked as closed. Otherwise above mentioned bug cycle gets repeated.(I will cover bug life cycle in other post)

Different tests are performed on individual modules and integration testing on module integration. These tests includes Compatibility testing i.e testing application on different hardware, OS versions,  software platform, different browsers etc. Load and stress testing is also carried out according to SRS. Finally system testing is performed by creating virtual client environment. On passing all the test cases test report is prepared and decision is taken to release the product!

So this was a brief outline of process of project life cycle.

Here is detail of each step what testing exactly carried out in each software quality and testing life cycle specified by IEEE and ISO standards:

Review of the software requirement specifications

Objectives is set for the Major releases

Target Date planned for the Releases

Detailed Project Plan is build. This includes the decision on Design Specifications

Develop Test Plan based on Design Specifications

Test Plan : This includes Objectives, Methodology adopted while testing, Features to
be tested and not to be tested, risk criteria, testing schedule, multi-
platform support and the resource allocation for testing.

Test Specifications
This document includes technical details ( Software requirements )
required prior to the testing.

Writing of Test Cases
Smoke(BVT) test cases
Sanity Test cases
Regression Test Cases
Negative Test Cases
Extended Test Cases

Development - Modules developed one by one

Installers Binding: Installers are build around the individual product.

Build procedure :
A build includes Installers of the available products - multiple platforms.

Testing
Smoke Test (BVT)  Basic application test to take decision on further testing

Testing of new features
Cross-platform testing
Stress testing and memory leakage testing.

Bug Reporting
Bug report is created

Development - Code freezing
No more new features are added at this point.

Testing
Builds and regression testing.

Decision to release the product
Post-release Scenario for further objectives.

Manual and Automation testing Challenges

Software Testing has lot of challenges both in manual as well as in automation. Generally in manual testing scenario developers through the build to test team assuming the responsible test team or tester will pick the build and will come to ask what the build is about? This is the case in organizations not following so-called ‘processes’. Tester is the middleman between developing team and the customers, handling the pressure from both the sides. And I assume most of our readers are smart enough to handle this pressure. Aren’t you?

This is not the case always. Some times testers may add complications in testing process due to their unskilled way of working. In this post I have added most of the testing challenges created due to testing staff, developing staff, testing processes and wrong management decisions.So here we go with the top challenges:

1) Testing the complete application: Is it possible? I think impossible. There are millions of test combinations. It’s not possible to test each and every combination both in manual as well as in automation testing. If you try all these combinations you will never ship the product
2) Misunderstanding of company processes:Some times you just don’t pay proper attention what the company-defined processes are and these are for what purposes. There are some myths in testers that they should only go with company processes even these processes are not applicable for their current testing scenario. This results in incomplete and inappropriate application testing.
3) Relationship with developers:Big challenge. Requires very skilled tester to handle this relation positively and even by completing the work in testers way. There are simply hundreds of excuses developers or testers can make when they are not agree with some points. For this tester also requires good communication, troubleshooting and analyzing skill.
4) Regression testing:When project goes on expanding the regression testing work simply becomes uncontrolled. Pressure to handle the current functionality changes, previous working functionality checks and bug tracking.
5) Lack of skilled testers:I will call this as ‘wrong management decision’ while selecting or training testers for their project task in hand. These unskilled fellows may add more chaos than simplifying the testing work. This results into incomplete, insufficient and ad-hoc testing throughout the testing life cycle.
6) Testing always under time constraint:Hey tester, we want to ship this product by this weekend, are you ready for completion? When this order comes from boss, tester simply focuses on task completion and not on the test coverage and quality of work. There is huge list of tasks that you need to complete within specified time. This includes writing, executing, automating and reviewing the test cases.
7) Which tests to execute first?If you are facing the challenge stated in point no 6, then how will you take decision which test cases should be executed and with what priority? Which tests are important over others? This requires good experience to work under pressure.
8 ) Understanding the requirements:Some times testers are responsible for communicating with customers for understanding the requirements. What if tester fails to understand the requirements? Will he be able to test the application properly? Definitely No! Testers require good listening and understanding capabilities.
9) Automation testing:Many sub challenges - Should automate the testing work? Till what level automation should be done? Do you have sufficient and skilled resources for automation? Is time permissible for automating the test cases? Decision of automation or manual testing will need to address the pros and cons of each process.
10) Decision to stop the testing:When to stop testing? Very difficult decision. Requires core judgment of testing processes and importance of each process. Also requires ‘on the fly’ decision ability.
11) One test team under multiple projects:Challenging to keep track of each task. Communication challenges. Many times results in failure of one or both the projects.
12) Reuse of Test scripts:Application development methods are changing rapidly, making it difficult to manage the test tools and test scripts. Test script migration or reuse is very essential but difficult task.
13) Testers focusing on finding easy bugs:If organization is rewarding testers based on number of bugs (very bad approach to judge testers performance) then some testers only concentrate on finding easy bugs those don’t require deep understanding and testing. A hard or subtle bug remains unnoticed in such testing approach.
14) To cope with attrition:Increasing salaries and benefits making many employees leave the company at very short career intervals. Managements are facing hard problems to cope with attrition rate. Challenges - New testers require project training from the beginning, complex projects are difficult to understand, delay in shipping date!
These are some top software testing challenges we face daily. Project success or failure depends largely on how you address these basic issues.

Enhancements in QTP 9.5

HP has made some major enhancements in QTP 9.5 over the previous versions. [For earlier versions, Please refer difference between QTP 8.2 and 9.2]
Environment Support:

  1. QTP 9.5 supports MS Vista 64 bit edition also, in comparison to QTP 9.2's support for 32 bit edition only.
  2. Support for omnipresent tabbed browsing is also introduced with this version.
Installation and Add-ins:
  1. QTP 9.5 offers all add-ins integrated with the core installation package. Though you still need to buy add-ins separately to get them activated.
  2. For installing QTP 9.5 you have to do a clean uninstall (as mentioned in the HP KB) of previous versions. That means, now on, you would not be able to upgrade from the previous versions.
QTP IDE:
A refreshing enhancement in QTP IDE GUI I liked this time was the introduction of the ability to see functions related to current tests. Whether you have an external file containing functions or they are inside a reusable actions, you would be able to see all of them at one place. Now no need to dig and scroll through the endless list of functions in your notepad!

Bitmap checkpoint: Earlier using bitmap checkpoint was a pain in a sense that a minor change in pixel and your test would fail. To increase the tolerance we have to go inside windows registry and change the required tolerance value. With QTP 9.5 HP has introduced support for tolerance level direct from the GUI. You can define tolerance in terms of RGB and/or pixels.

Web Add-in Extensibility: Using this feature you can configure and extend the support to those 3rd party custom web controls ( and new technologies like AJAX) which were not supported with the earlier versions. You need to possess fair amount of JavaScript knowledge to handle this. How much help this feature really provide is yet to be seen!


Note: This is not a complete list of enhancements. For detailed list refer Help > What's new in QTP

Difference between QTP8.2 and QTP9.0/QTP9.2

Over and above features provided with QTP 9.0 , QTP 9.2 provides following features:

Mercury Screen Recorder :
Capture your entire run session in a movie clip or capture only the segments with errors, and then view your movie from the Test Results window.
Dynamic Management of Object Repositories:
QuickTest now has a new RepositoriesCollection reserved object that you can use to programmatically manage the set of object repositories that are associated with an action during a run session.

Over and above features provided with QTP 8.2 , QTP 9.0 provides following features:

Object Repository Manager:
You can use the Object Repository Manager to manage all of the shared object repositories in your organization from one, central location. This includes adding and defining objects, modifying objects and their descriptions, parameterizing test object property values, maintaining and organizing repositories, and importing and exporting repositories in XML format.
You can open multiple object repositories at the same time. Each object repository opens in its own resizable document window. This enables you to compare the content of the repositories, to copy or move objects from one object repository to another, and so forth.
Object Repository Merge Tool:
You can use the Object Repository Merge Tool to merge the objects from two shared object repositories into a single shared object repository. You can also use the Object Repository Merge Tool to merge objects from the local object repository of one or more actions or components into a shared object repository.

When you merge objects from two source object repositories, the content is copied to a new, target object repository, ensuring that the information in the source repositories remains unchanged.

If any conflicts occur during the merge, for example, if two objects have the same name and test object class, but different test object descriptions, the relevant objects are highlighted in the source repositories, and the Resolution Options pane details the conflict and possible resolutions.
Multiple Object Repositories per Action or Component:
QuickTest provides several options for storing and accessing test objects. You can store the test objects for each action or component in its corresponding local object repository, which is unique for each action and component. You can also store test objects in one or more shared object repositories that can be used in multiple actions and components. Alternatively, you can use a combination of objects from the local object repository and one or more shared object repositories. You choose the combination that matches your testing needs.
XML Object Repository Format:

QuickTest now enables you to import and export object repositories from and to XML format. This enables you to modify object repositories using the XML editor of your choice and then import them back into QuickTest. You can import and export files either from and to the file system or a Quality Center project (if QuickTest is connected to Quality Center).
Function Library Editor:

QuickTest now has a built-in function library editor, which enables you to create and edit function libraries containing VBScript functions, subroutines, modules, and so forth, and then call their functions from your test or component.
Handling Missing Actions and Resources:
Whenever a testing document (test, component, or application area) contains a resource that cannot be found, QuickTest opens the Missing Resources pane and lists the missing resource(s). For example, a test may contain an action or a call to an action that cannot be found; a testing document may use a shared object repository that cannot be found; or a testing document may use a object repository parameter that does not have a default value. In all of these cases, QuickTest indicates this in the Missing Resources pane, enabling you to map a missing resource to an existing one, or remove it from the testing document, as required.
Source: What's New in Quick Test Professional--QTP Documentation